50 Nota Benes in Tender and Contract Documentation

Go to End

Note

27/2/2026: Updated for HKIS QSD PQSL event on the same day.

20/3/2022: Punctuation style revised. Numbering corrected. Items 5 and 6 revised.

21/1/2020: Expanded for HKIS QSD PQSL event on the same day.

25/12/2014: Posted on this website.

3/3/2012: Presented by Mr. K C Tang at One Day Seminar on Contract Management 2012.

General

1. Identify the ultimate purposes of preparing tender documents and serve the purposes:

  • Get a good contractor
    • What is meant by good? Quality, time, safety, resources (people, equipment, money), claims, attitude.

(revised, 27/2/2026) 

  • Get a good price
    • What is meant by good? Lowest? Adequate?

(revised, 27/2/2026) 

  • Get the desired quality
  • Permit sufficiency of time and price
  • Reduce ambiguity, arguments and disputes
  • Reduce unexpected cost and time overruns
  • Reduce unexpected claims
  • Allow for changes
  • Allow easy calculation of costs of changes
  • Share risks clearly
  • Start work as soon as possible irrespective of degree of completion of design
  • etc, etc.

2. Comply with client’s procedures:

  • Government departments
    • Procedure oriented, stringent procedures, internal practice manuals, personal preferences

(sub-point added, 27/2/2026)

  • Professional developers
    • Business oriented

(sub-point added, 27/2/2026)

  • Contractors (when sub-letting).

3. Determine appropriate tender packages and tendering programme:

  • Site survey, ground investigation and demolition usually under separate advance contracts
  • Split between site formation, piled foundations, substructure, basement and superstructure
  • Split between main contract, nominated sub-contracts and supply contracts
  • Split into domestic sub-contracts and supply contracts
  • Design development in stages with separate tenders in stages
  • Full design development for single contract package for all
  • Single point of responsibility vs splitting.

(last point added, 27/2/2026)

4. Choose appropriate contractual arrangement and understand their different implications:

  • Design-bid-build vs design and build (plus operate)
  • Management contractor vs construction manager

(point added, 27/2/2026)

  • Nominated vs domestic
  • Supply only (sales contract) vs supply and install (works contract)
  • Collaborative, partnering
  • Lump sum, remeasurement, rates only, cost plus, target cost with or without pain / gain share

(revised, 27/2/2026)

  • NEC contracts with different concepts, procedures and language.

(last point added, 27/2/2026)

5. Observe confidentiality and avoid collusion:

6. Avoid and declare conflict of interest.

7. Ensure fair competition:

  • Waste of tendering time and resources
  • Loss of trust
  • Loss of tenderers.

8. Do not trust computer and people:

  • Garbage in garbage out
  • Reliability of Client's staff
  • Change of Client's staff and challenge of past decisions
  • Decisions must be within reasons and rationale be properly documented.

Documentation generally

9. Identify which standard documents and templates to use:

  • In-house
  • Client's
  • Lead consultant's
  • Changing standards
  • Lag time in releasing changes
  • Past projects
  • Most up to date standards preferred to past projects'.

10. Ensure adequate representation:

  • Ensure sufficiency of price and time
  • Give all information to ascertain entire quality and quantities of the work and services required for the completion of the Contract
  • Give full knowledge of site conditions and problems which may affect price and time
  • Give fewer items to reduce chances of adding prices vs give more items to ensure no shortfall.

11. Avoid ambiguities, discrepancies, inconsistent terminology, etc.:

  • Client, Employer
  • Architect, Engineer, Lead Consultant, Project Manager, Contract Administrator, Supervising Officer
  • Sub-Contractor vs Contractor vs Builder in Technical Specification
  • Works, works, work
  • Rate for
  • Quantity of
  • Tender Documents, Tender Document
  • General Specification, Particular Specification, Technical Specification
  • Schedule of Rates and Summary of Tender in pre 2005/2006 Standard Forms of Building Contract
  • Schedule of Quantities and Rates in 2005/2006 Standard Forms of Building Contract
    • Who measures the quantities?
    • Now changed back to Schedule of Rates in 2025 Standard Form of Building Contract

(sub-points added, 27/2/2026)

  • Damages, damage
  • Shall, will, should, would
  • Precedence of documents
    • Mutually explanatory or clear precedence to be stated?

(sub-point added, 27/2/2026)

  • Precedence of contents.
    • Particulars over general, later over earlier.

(sub-point added, 27/2/2026)

12. Avoid repetition of same provisions at different parts of documents:

  • inconsistency, duplicated effect when making changes

(sub-point added, 27/2/2026)

13. Check correct page headers, footers, covers, contents, page numbers, item references, etc., correct use of units, correct cross referencing of document, page and clause numbers:

  • Who does what for Technical Specification.

Tender documentation

14. State deviations from standard form of contract, standard specification, standard method of measurement, etc.:

  • Special Conditions of Contract
  • Particular Specification
  • Preambles
  • Standard Preambles and Special Preambles
  • Preamble notes in the Bills of Quantities, Schedule of Rates, Schedule of Quantities and Rates.

15. Notify Client of important features and seek approvals:

  • Particulars to be specified in the Form of Tender: alternative tenders, times for completion, tender validity period
  • Particulars to be stated in the Appendices to the Conditions of Contract
  • Insurance arrangement, limits of indemnity
  • Bond amounts
  • Application of Security of Payment Ordinance

(three sub-points added, 27/2/2026)

  • Really special Special Conditions of Contract.

16. Allocate risks appropriately:

  • Best one to manage?
  • Best one to bear / take?

17. Watch out that harsh terms may not be workable:

  • Harsh terms enforceable if clear beyond doubt and agreed by the contract parties voluntarily
  • Except when forbidden by law
  • Except when not clear enough to override common interpretation
  • Harsh terms would diminish the authority of the Contract Administrator who is bound by the loss of authority
  • "Impose harsh terms in contract and relax when the need arises" may turn out to be a deadlock or a room for corruption.

 (last point revised, 27/2/2026)

18. Check that specified brands and models are still in production:

  • Government contract would not specify brands and models without prior approval.

19. Be specific as to which one to choose out of the different choices available from the standard.

20. Define possession, commencement and completion times and phases properly:

  • Date for possession
  • Date for commencement
  • Date for completion
  • Site phasing vs works phasing
  • Zones/ phases / sections / stages
  • "for" vs "of", "from" vs "after" vs "on"

(last sub-point revised, 27/2/2026)

21. Estimate genuinely the rates of liquidated damages for delay:

  • "of" not "for"
  • Avoid double penalty
  • Suppose the rate of LD for Section 2 is the same as that for the earlier Section 1
  • If the rate is equally applicable for a delay occurring before or after the completion of Section 1, this is very likely to be a double penalty because the loss and expense before or after the completion of Section 1 should be different.

22. Specify procurable types of bonds and set affordable level of bond amounts:

  • Conditional bond (on-default) bond
  • On-demand bond.

23. Set procurable levels of insurance excesses.

24. Check that descriptions of Bills of Quantities or Schedule of Rates or Schedule of Quantities and Rates or Schedule of Works sufficiently cover and match the requirements as described in the Specification and/or as shown on the Drawings.

(revised, 27/2/2026)

25. Divide into smaller items for pricing if a bigger item is likely to be partially varied:

  • Door frames and door leaves, more expensive ironmongery, manholes and covers, curtain wall glazing

(sub-point added, 27/2/2026)

26. Suitable provisional quantities:

  • Avoid small provisional quantities to avoid high rates
  • Add items for machine bases, plinths, trial pits outside site, etc. obtain rates

(sub-point added, 27/2/2026)

27. Ensure that prime cost rates are set at appropriate levels:

  • Implication of excessive deviations of rates on wastage and profit and overheads.

28. Ensure that the correct Prime Cost and Provisional Sums are carried forward to the Summary.

29. Specify as optional if firm quantity items are likely to be omitted or added:

  • "optional" <> "provisional".

Tendering

30. Choose suitable tenderers:

  • Experience
  • Specialty
  • Technical capability
  • Financial capability
  • Safety, claims and disputes track records
  • Innovation
  • Pre-qualifications
  • Newspaper advertisement
  • Open tendering
  • Selective tendering.

31. Give sufficient time for tendering:

  • Watch out long holidays
  • Give sufficient time after tender addendum
  • Extend tender return date.

32. Permit site visits individually:

  • Site visits in groups only if essential.

33. Arrange for tender briefing only if really necessary and in groups.

34. Give common answers to queries raised by one to all tenderers.

35. Disregard late tenders.

Tender analysis

36. Check tenders returned:

  • Sufficiency of tender submissions
  • Correctness of arithmetic
  • Compatibility of submitted programmes with specified requirements
  • Suitability of specifically stated delivery and installation periods
  • Qualifications and deviations
  • Missing or duplicated items or unreasonable quantities in case of Schedule of Rates and Schedule of Quantities and Rates prepared by the Tenderers
  • General price levels
  • Front loading
  • Rates for items with small quantities
  • Rates for dayworks and mark-ups
  • Incorrectly priced high or low rates
  • Items not priced
    • Need to confirm included?
    • Deemed included or deemed priced as "0"?
  • Similarity of rates quoted by different tenderers
  • Good prices when the tender sums are within 5% of each other and the pre-tender estimate?

(last 3 sub-points added, 27/2/2026)

37. Consider reasonable qualifications.

38. Rationalize incorrectly high or low rates:

  • For additions only or for omissions and additions?
  • For contract quantities also - re-pricing with rationalised rates keeping the Tender Sum unchanged? Benefits if adopted.

(2 sub-points added, 27/2/2026)

39. Issue post clarifications to clarify or rectify with no change to the tender sums.

40. Conduct tender interviews with no indication of tender priority.

41. Do not accept uninvited changes to tender sums or rates and prices, and post tender exclusions.

42. Handle post tender changes and best offer invitation with care and fairness:

  • Requst for best offer without any changes to the tender requirements?

(sub-point added, 27/2/2026)

  • Revised offer and best offer in sealed envelopes
  • Treatment of discounts.

Contract award

43. Award to tenders financially and technically capable.

44. Award within the tender validity period:

  • Extend tender validity period.

45. Choose properly between letter of intent and letter of acceptance.

46. Ask for signed Form of Warranty before accepting a sub-contract tender.

47. Specify how discounts should be applied, and ensure discounted all-in rates not lower than prime cost rates.

48. List out documents to form the Contract Documents.

49. Ask for counter-signature of letter of intent and letter of acceptance since they may be regarded as counter-offers requiring acceptance.

50. Sign formal contract documents before things go sour.

Note that there are actually more than 50 Nota Benes.

End of Page