Note 註
29/1/2024: Revised.
19/2/2023: Revised.
20/12/2014: Moved from wiki.
-> TopIntro 介紹
-> TopNeed 需要
- Quantity Surveyors need to have knowledge to advise on the procurement strategy and contractual arrangement.
工料測量師需具備就採購策略和合約安排提供建議的知識。
(added, 19/2/2023)
-> TopWhy contract out? Why call for tenders? 為什麼要外包? 為什麼要招標?
- Find someone to do it for you.
找人幫你做 - Someone:
該人:- More capable
較有能力 - Statutorily qualified
有法定資格 - Less costly.
成本較低
- More capable
- Accountability in case of joint venture.
合資企業的問責。
When to decide? 什麼時候決定?
- As early as when the first project programme is developed.
早在第一個項目計劃制定時。
Which types of contractual arrangement? 哪些類型的合同安排?
- Traditional or special? 傳統還是特殊?
Classification of contract types based on 不同的合同形式的分類
-> TopContract scope 按承包範圍分類
- Design.
設計 - Build.
施工 - Design and build / turnkey / package deal / engineering, procurement and construction:
設計和施工 / 交鑰匙 / 統包 / 設計、採購和施工- 優點:
- 工程太簡單不必請建築或工程師。
- 取得承包方特有而一般的建築或工程師沒有的特殊設計優點。
- 取得承包方特有的建造方法或產品。
- 設計及施工時間可重疊,相應縮短了工期。
- 總的來說可省一些設計費。
- 由承包方單一負責,而減少多方參與責任不清的程度。有時這個好處被視為最大優點,使到根本不存在上述2及3點的工程都採用。
- 總造價較有保証。
- 可規定成品能滿足意向功能,此乃高於一般只需行使合理技能的標準。
- 在全包的情況下,承包方的索賠機會較少。
- 缺點:
- 發包方的要求寫得太死,承包方沒有自由設計的空間。
- 發包方的要求寫得太鬆,不能表達到預期的成果,或有空間給承包方索賠。
- 發包方不能隨意改動要求。
- 發包方對設計的改動要求,是屬於原要求範圍內還是超出範圍,往往會有爭議。
- 真的超出範圍而需計算增加費用時,因可能要與一個尚未設計好便改動了的方案比較,難度比較大。減內容亦有類似的問題。
- 鑑於總造價是基本封頂的,發包方會傾向在具體設計時增加內容及取最高的標準,令承包方吃虧。
- 鑑於總造價是基本封頂的,承包方會傾向在具體設計時盡量省料及取最低的標準,令發包方吃虧。
- 雙方合作不愉快時,爭議反為多了。
- 優點:
- Design, build and operate.
設計、施工、營運
Contract relationship 按承包關係分類
- Traditional main contracting.
傳統總承包 -
Management contracting.
管理承包
-
Construction manager.
施工管理經理
Pricing basis 按投標基礎分類
- Based on firm bills of quantities, with reference to drawings and specification.
按確定工程量清單,參閲圖紙及規範 - Based on provisional bills of quantities, with reference to drawings and specification.
按暫定工程量清單,參閲圖紙及規範 - Based on drawings and specification, without bills of quantities. Submitted as quotations / schedule of rates / schedule of quantities and rates / activities schedules.
只按圖紙及規範,不含工程量清單。以報價單 / 單價表 / 有量單價表 / 活動表提交 - Based on pre-priced schedule of rates, competing on adjustment percentages.
按預設單價表,競爭調整費率
Pricing nature 按標價形式分類
- Lump sum total, with unit rates.
總價報價,輔以單價 - Rates only, without total.
單價報價,無總價 - Percentage.
費率報價
Degree of risks 按風險程度分類
- Fixed price.
固定價 - Price with fluctuation.
可調價 - Cost plus fee (lump sum fee, fixed percentage fee, scaled percentage fee, sharing).
成本加服務費(一筆過、固定費率、遞減費率、分成) - Ceiling price / Guaranteed Maximum Price.
封頂價- Demarcation between Costs and Fee.
成本與服務費的劃分
- Demarcation between Costs and Fee.
Funding arrangement 融資安排
- All funded by the employer.
- 全由發包方安排
- Public-private partnerships:
公私營合作- Build–Operate–Transfer, BOT
民間興建營運後轉移模式 - Operate–Transfer, OT
營運後轉移模式 - Build-Operation-Own, BOO
興建-營運-擁有模式 - Reconstruction-Operation-Transfer, ROT
民間重建營運後移轉模式 - Private finance initiative (UK)
民間融資提案 - Private Sector Participation Scheme (HKHA)
私人機構參建居屋計劃 (居屋) (香港房屋委員會) - References:
- https://en.wikipedia.org/wiki/Public%E2%80%93private_partnership
- An Introductory Guide to Public Private Partnerships (PPPs) March 2008 (Second Edition) published by the Efficiency Unit of the Government of Hong Kong SAR
- Practical Guide to Public Private Partnership (PPP) Projects published 2009 by the HKIS
- Build–Operate–Transfer, BOT
Degree of commitment
- One-off contracts.
- Term contracts.
- Serial contracts.
- Standing offers.
- Framework contracts:
https://www.designingbuildings.co.uk/wiki/Framework_contract - Prime contracts:
https://www.designingbuildings.co.uk/wiki/Prime_contract
How to package contracts?
- Optimum balance between the time required to complete every design and the time required to construct.
- Optimum balance between single line responsibility and more control over choosing sub-contractors and suppliers.
- Specialist works by specialist contractors/sub-contractors.
- Responsibility for delivery time and wastage to be watched out if nominated supply contracts are used.
Usual contract packaging 總包分包的分拆
-
Site Survey Contract.
現場勘察合同
-
Ground Investigation Contract.
地質勘察合同
- Demolition Contract.
拆卸工程合同 - Piling Contract.
基樁合同 - Main Contract.
主合同 - Sub-Contract.
分包合同 - Supply Contract.
供應合同 - Other Direct Contracts.
其他獨立合同
Which form of contract?
- Private or public?
- Domestic or international?
- Standard form or specially drafted?
- Old or new versions?
- With how much amendments?
- How harsh?
- See Forms of Contract.
Risks sharing 風險的分擔
- Soil conditions.
土質 - Underground obstructions.
地下障礙物 - Phased possession of site and completion.
分階段交付工地及竣工 - Time for completion.
工期 - Liquidated damages.
誤期賠償 - Grounds for extension of time.
工期延長的許可原因 - Grounds for monetary claims.
索賠的許可原因 - Insurances and bonds.
保險及擔保 - Defects liability period / defects rectification period.
保修期 - Payment terms.
付款辦法