Query list 编标问卷

Table of Contents

Query list
编标问卷

  1. During the course of BQ production, there is bound to be uncertainty of information either in respect of the project particulars or in respect of the Drawings and Specification
    编制工程量清单时,常会碰到工程细节、图纸或工料规范有不清楚的地方
  2. Clarify with the Architects or Engineers using telephone conversation or email
    先以电话或电邮询问设计单位
  3. Write down the answers obtained on a query list
    用编标问卷书面记录答案
  4. Make reasonable and confident assumptions on the query list prior to receipt of answers
    未有答案前,可把有信心的合理假设写在问卷上
  5. Refer to the following sample form: 
    参考以下格式例:
  6. To avoid grammatical mistakes and to reduce the subsequent time to make corrections, write the queries in note form which is still understandable, particularly when assumptions or answers have been made such that a query and assumption or answer can be read together to make sensible and complete meaning
  7. Dispatch the query list from time to time to the Architects or Engineers for answering outstanding queries or confirming answered queries and for record
    定期发出问卷以便取得未有的答案或确定已有的答案及做为记录
  8. Chase for the return of the query list with answers within a reasonable time
    跟进在合理时间之内有回复
  9. Reflect the final answers in the Bills of Quantities
    把最后的答案在工程量清单反映